ReVision Energy will be installing solar panels on buildings 148, 152, 136, 127, 135, 131, 161, 165 and 169 beginning on Monday, August 27, 2018. The entire project will take between 2 and 3 weeks to complete. They will not need access to your apartments but will be on the roofs which will be noisy at times. Their working hours will be between 8:00 a.m. and 4:30 p.m.
Lenny, Keene Housing’s Working Foreman, will be onsite if you have any questions, comments or concerns during the installation. We are hosting a Question and Answer session at 11:00 a.m.in the Community Room at 105 Castle Street on Wednesday, August 22, 2018.
Thank you in advance for your cooperation and patience. If you have any questions, please contact Sandy Clark at 352-6161 or email sclark@keenehousing.org.