Beginning on or around April 1st, the first phase of this multi-phase project will begin with Guyer Roofing removing all the old roofs and installing new roofing on every building.
Buildings 15 and 16 will have their dryer vents re-routed to go out the side of the buildings rather than the roof. The Contractor for this part of the project is still to be determined and we will send you notice as soon as that is finalized.
Re-Vision Energy will be installing solar panels on all but the Family Activity Center’s roofs this Spring/Summer and again we will send you notice once those dates are finalized.
We are also in the process of hiring a General Contractor to oversee the replacement of electric thermal heaters in the bedroom and living room with heat/air conditioner pumps. Yes, you will have central air! In addition, we are replacing your front and back doors (keys will remain the same), new rear storm/screen doors and replacement of the front cement porches and railings on apartments 8#6, 15#5, 15#6, 21#2, 21#6 and 25#6.
We will schedule an informational “pizza dinner” meeting once we have the General Contractor on board so stay tuned.
If you have any questions, please call Sandy Clark at 352-6161 or email sclark@keenehousing.org. Thank you in advance for your patience and cooperation!