Forest View Heat Pump Project – Building 24

Post on July 12, 2019

Beginning on Monday, July 15, 2019, Cheshire Builders will drill holes and install brackets for heat pump units, drill the outside of the building for the condensate lines and install new front, back and screen doors.  This work is expected to take two weeks.

Gary Jackson Heating will install the heat pumps on or around August 9, 2019.

Please make sure that the workers have clear access to the entire apartment as they will be working in just about every room.

Residents do not need to be present during the work. Keene Housing maintenance staff, Chris and/or Josh, will let the workers into each apartment.

Thank you for your patience and cooperation.