Top

Forest View Heat Pump Project – Building 16

Post on July 8, 2019

Beginning on Wednesday, July 10, 2019 Elm City Electric will be replacing the electrical panel in the kitchens of Building 16.

Cheshire Builders will drill holes and install brackets for heat pump units, drill the outside of the building for the condensate lines and install new front, back and screen doors.  This work is expected to take two weeks.

Gary Jackson Heating will install the heat pumps on or around July 31, 2019.

Please make sure that the workers have clear access to the entire apartment as they will be working in just about every room.

Residents do not need to be present during the work. Keene Housing maintenance staff, Chris and/or Josh, will let the workers into each apartment.

Thank you for your patience and cooperation.

If you have any questions, please contact Sandy Clark at 352-6161 or email sclark@keenehousing.org.

Please direct press inquiries to
Amy Wright
603-352-6161 x324